CANVAZ Palette timeline in Phuket: the schedule and what is still open

In shortConstruction at CANVAZ Palette Cherngtalay starts in November 2026 and the project is expected to complete around May 2028, followed by condominium registration and handover. EIA approval and the construction permit are in progress — we confirm the current status before your contract payment falls due.

5 facts about this
  • Now → November 2026: EIA submission and construction permit; sales are open, booking deposits taken
  • November 2026: construction commences
  • Around May 2028: expected completion — roughly an 18-month build
  • After completion: condominium registration, then unit transfer and the 50% final payment
  • Your 30% contract payment and 20% downpayment fall due before the building exists — which is the whole risk and the whole discount

Updated: · how the payments line up

Stage by stage

StageWhenWhat it means
Sales launch2026Open now — 71 apartments with a published price, Buildings A and B, floors 1, 3, 5 and 6
EIA and construction permitin progressWe confirm the current status before your contract payment falls due
Construction commencesNovember 2026The developer’s own date
Expected completionaround May 2028Developer’s target, not a contractual guarantee
Condominium registrationafter completionRequired before any unit can transfer to a buyer
Transfer and final 50%after registrationSinking fund and first year of common area fee are due at the same moment

These are the developer’s own dates. Construction starts in November 2026 — until then the show unit is the place to see the finishes and the layouts in full size.

Straight talk

What “pending EIA” actually means for you

  • An EIA is an environmental impact assessment and it is a condition of the construction permit. Until it clears, the November 2026 start date is a plan rather than a date.
  • Ask what happens to your money if it is refused or delayed. The answer is in the contract, not the brochure — look for the refund mechanism and any deadline attached to it.
  • Time your payments to milestones you can verify. A contract payment falling due before the permit is issued is a negotiation point.
  • Off-plan in Thailand routinely runs late. If May 2028 is load-bearing for you — a school year, a visa, a rental start — build in a buffer of two to three quarters.

Get the current approval status

We ask the developer where the EIA and the construction permit stand this month and send you the answer with the paperwork.

Where should we send it? No calls unless you ask:

We reply within 10 minutes during business hours (Phuket time). No newsletters; your details are never sold or passed on for marketing.

Prefer to message us? WhatsApp · Telegram

WhatsApp Choose a unit